Davao City WTE project nears bidding stage; completion targeted in 2029
Davao City WTE project nears bidding stage; completion targeted in 2029
The proposed Waste-to-Energy (WTE) project of Davao City is expected to move closer to implementation as the City Council is scheduled to approve on third and final reading an ordinance adopting its bidding documents during its regular session on Tuesday, November 17.

Councilor Temujin “Tek” Ocampo, chair of the Committee on Environment and Natural Resources, said the passage of the ordinance will pave the way for the commencement of the competitive bidding process for the project.

“Once this is already an ordinance, we expect that the bidding process for the Waste-to-Energy project will commence,” Ocampo said.

He said construction will begin at the designated project site in Biao Eskwela, Tugbok District, once the winning bidder is identified and the necessary requirements are completed.

The project is targeted for completion by December 2029 and is expected to generate approximately 11 megawatts of electricity while processing municipal solid waste daily.

Ocampo described the WTE facility as one of the pet projects of then-Mayor and now Vice President Sara Duterte, which is now moving toward implementation under the administration of Mayor Sebastian “Baste” Duterte.

The project is supported by a grant from the Government of Japan under agreements signed on March 20, 2018. It aims to strengthen the city's solid waste management system through the treatment of residual waste and the recovery of energy.

The bidding documents cover the invitation for bids, bidding procedures, technical and operational requirements, and proposed contractual arrangements for the engineering, construction, operation and maintenance of the facility under a Build-Transfer-Operate (BTO) framework.

However, Ocampo clarified that adopting the bidding documents does not automatically constitute an award of the project to any bidder. The selection will still undergo competitive bidding and comply with applicable Philippine laws and Japanese grant-aid requirements.

The project is expected to provide Davao City with an alternative approach to managing residual waste while generating electricity from waste materials. BuyMaps

Davao City First District Councilor Tek Ocampo

Ruth Palo
Official Verified Account

What's your reaction?

Facebook Conversations